December 16 2024

Project launch

January 29 2025

Community Conversation event

January 31 2025

Public engagement ends

March 14 2025

What We Heard Report summarizing feedback

The report outlining all of the feedback received from the public, What We Heard Report, will be published in early February.

May 2025

Decision, next steps & project update

Residents and stakeholders will be provided with an update about potential next steps and timelines.

August 2025

Changes implemented to create one-way traffic flow

  • 11 Street South to change to one-way traffic going southbound
  • 12 Street South to change to one-way traffic going northbound