September 2024
Fall 2024 - Phase 1 Project Initiation
Preparation of a project engagement plan, design development, and review.
December 2025
Phase 2 - Engagement
Share preliminary design and get feedback from directly impacted stakeholders through virtual and in-person engagement sessions.
July 2025
Phase 3 - Design Completion Summer, 2025
Finalize plan based on stakeholder feedback and technical considerations through (Winter/Spring 2025).
December 2025
Phase 4 - Tender for Construction, Winter 2025
July 2026
Phase 5 - Construction, Winter 2026 - 2027