September 2024
Fall 2024 - Phase 1 Project Initiation
Preparation of a project engagement plan, design development, and review. 
 
 
 
January → April 2025
Phase 2 - Engagement
Share preliminary design and get feedback from directly impacted stakeholders through virtual and in-person engagement sessions.
 
 
 
August 2025
Phase 3 - Design Completion Summer 2025
Finalize plan based on stakeholder feedback and technical considerations through (Winter/Spring 2025). 
 
 
 
August 2025
Phase 4 - Tender for Construction, Summer 2025
 
 
July 2026
Phase 5 - Construction, Summer, 2025 - 2026