3 Avenue South - 4 Street to 8 Street Reconstruction
Consultation has concluded
This project is the reconstruction of 3 Avenue South, from 4 Street South to 8 Street South in Downtown Lethbridge. Originating in the Public Realm and Transportation Study (PRATS) (2012), this project was approved by City Council in the current Capital Improvement Program (CIP) 2018-2027, under D-22.
The vision for 3 Avenue is to create a more vibrant downtown and an environment that offers a safe, lively, accessible and attractive place to work, live, shop, learn and play. This will be achieved through design techniques known as streetscaping, which includes street furniture such as benches, planters, trees, garbage cans, andContinue reading
This project is the reconstruction of 3 Avenue South, from 4 Street South to 8 Street South in Downtown Lethbridge. Originating in the Public Realm and Transportation Study (PRATS) (2012), this project was approved by City Council in the current Capital Improvement Program (CIP) 2018-2027, under D-22.
The vision for 3 Avenue is to create a more vibrant downtown and an environment that offers a safe, lively, accessible and attractive place to work, live, shop, learn and play. This will be achieved through design techniques known as streetscaping, which includes street furniture such as benches, planters, trees, garbage cans, and decorative street lighting. A general promotion of mobility and accessibility will be included through elements such as raised parking areas; bulb-outs at the intersections to reduce pedestrian crossing distances and increase visibility; widening of sidewalks; and a multi-use pathway. A unique design characteristic includes a raised intersection at 6 Street South which will enhance the user experience for festivals and special events.
The City would like to involve all stakeholders in the development of a construction staging plan that balances the needs of the businesses, residents, and the community to minimize impact during construction and maintain access.
-
Construction get's Underway in 2022
Share Construction get's Underway in 2022 on Facebook Share Construction get's Underway in 2022 on Twitter Share Construction get's Underway in 2022 on Linkedin Email Construction get's Underway in 2022 linkConstruction for 2022 on 3rd Avenue S has begun and we are anticipating construction completion in June 2022.
Business is Open, we encourage the public to take a walk on 3rd Ave S to visit the small businesses to show your support.
-
How to Get Around Downtown
Share How to Get Around Downtown on Facebook Share How to Get Around Downtown on Twitter Share How to Get Around Downtown on Linkedin Email How to Get Around Downtown linkAs we move into mid-October there have been many changes on 3rd Avenue S as well as the Festival Square Area on 6th Street. Take a look at the map to find out the best places to park and how to get around during construction in October and November 2021.
-
Construction get's underway in 2021
Share Construction get's underway in 2021 on Facebook Share Construction get's underway in 2021 on Twitter Share Construction get's underway in 2021 on Linkedin Email Construction get's underway in 2021 linkAs we kick off Construction for 2021 on 3rd Avenue S you will find that we have brightened up the construction fencing this year with some beautiful artwork.
Business is Open, we encourage the public to take a walk on 3rd Ave S to visit the small businesses to show your support and while you are in the area check out the incredible art displayed around the construction area.
-
A Streetcar Named Desire: 3rd Avenue project unearths piece of history
Share A Streetcar Named Desire: 3rd Avenue project unearths piece of history on Facebook Share A Streetcar Named Desire: 3rd Avenue project unearths piece of history on Twitter Share A Streetcar Named Desire: 3rd Avenue project unearths piece of history on Linkedin Email A Streetcar Named Desire: 3rd Avenue project unearths piece of history linkDid you know that Lethbridge used to have a streetcar system? It was in operation from 1912 to 1947 and buried under the road around 1949. Last week, the 3rd Avenue reconstruction project got under way and part of the track system was revealed. Watch the video below to learn more about the streetcars rich, and humorous history in downtown Lethbridge.
-
3 Avenue Reconstruction gets underway
Share 3 Avenue Reconstruction gets underway on Facebook Share 3 Avenue Reconstruction gets underway on Twitter Share 3 Avenue Reconstruction gets underway on Linkedin Email 3 Avenue Reconstruction gets underway link3 Avenue Reconstruction gets underway
An exciting project in Downtown Lethbridge will get underway this week when reconstruction starts on 3 Avenue South from 4 to 8 Street.
As one of the oldest streets in Lethbridge, 3 Avenues South has always been a vital part of the community, once serving as the main east/west highway through the city. This project will not only provide important utility and infrastructure upgrades to the street but it will also enhance the aesthetics of 3 Avenue.
“We are really excited to get started on the 3 Ave. S. Reconstruction project,” says Project Manager, Crystal Scheit from the City’s Transportation Department. “Over the next two years, major enhancements will be made to our downtown by installing reliable infrastructure and creating a street that is a safe, lively, accessible and beautiful.”
Originating in the Public Realm and Transportation Study (PRATS) (2012), this project was approved by City Council in the current Capital Improvement Program with a total budget of just over $10 million.
“Despite the impacts of COVID-19, Council decided to move forward with this important project,” says City Councillor Mark Campbell. “This is vital to the revitalization of Downtown and the project will help with our continued economic recovery.”
When completed, 3 Avenue will boast Lethbridge’s first streetscaped design. Streetscaping brings together all of the elements that will give 3 Avenue character and make it functional like lighting, seating, paving materials and plants/trees.
“This is a major construction project and we understand that this will be disruptive but we’re make every effort to minimize the impact on residents and the businesses.” says Andrew Malcolm, Urban Revitalization Manager for the City of Lethbridge. “We’ve done extensive public and stakeholder engagement leading up to the launch of the project and will continue that through the duration of the construction to keep everyone updated on progress.”
Adding the 3 Ave Reconstruction project to the overall downtown revitalization efforts will attract more people and activity to the city centre which will, in turn, contribute to a clean and safe downtown.
Current Construction Impact
Starting Wednesday, July 29, 3 Avenue South will be closed from 6 Street to 7 Street as construction work begins. Residents should expect closures rotating throughout the project area from now until the project completion expected in the fall of 2021. Motorists are advised to drive with caution in this area and follow posted detours.
Who's listening
-
Phone 403-320-3902 Email crystal.scheit@lethbridge.ca
Photos
Project Timeline
-
Project Initiation
3 Avenue South - 4 Street to 8 Street Reconstruction has finished this stageDecember 2016
-
Preliminary Design
3 Avenue South - 4 Street to 8 Street Reconstruction has finished this stageThe City completed a preliminary design for 3 Avenue South between Scenic Drive South and Stafford Drive South. Fall 2017
-
Detailed Design
3 Avenue South - 4 Street to 8 Street Reconstruction has finished this stageThe City is completing a detailed design for 3 Avenue South between 4 Street South and 8 Street South. Winter/Spring 2019
-
Construction Staging Plan
3 Avenue South - 4 Street to 8 Street Reconstruction has finished this stageThe City will consult with adjacent businesses, residences, property owners and other stakeholders to finalize a construction staging plan. Fall/Winter2019
-
Construction
3 Avenue South - 4 Street to 8 Street Reconstruction is currently at this stageSummer 2020 - Spring 2022